12 Cubic Yards of Limestone Screenings in Tons
12 cubic yards of limestone screenings in tons works out to about 16.8 tons using a planning weight of 1.4 tons per yard. Real loads land between roughly 15.6 and 18.0 tons depending on stone size, fines and moisture. That is about 33,600 pounds.
Volume and tonnage calculator →The conversion
- Yards × tons per yard: 12 × 1.4 = 16.8 tons.
- Low end: 12 × 1.3 = 15.6 tons.
- High end: 12 × 1.5 = 18.0 tons.
Quarries can tell you the weight per yard for their own product; use it if you have it.
What 12 yards covers
| Depth | Square feet |
|---|---|
| 1 in | 3,888 |
| 2 in | 1,944 |
| 3 in | 1,296 |
About limestone screenings
Screenings hold moisture and can crust over. Use them in thin layers over a compacted stone base instead of as a thick layer on their own.
Hauling 12 yards
Plan the delivery around 16.8 tons: two or more trucks in most areas. A pickup is a poor fit for anything past a fraction of a yard; see how much gravel a half-ton pickup can carry.
Before you order
- Confirm whether the yard prices limestone screenings by the ton or by the yard.
- Add about 10 percent for compaction and uneven ground.
- Clear a firm spot for the truck to dump.
The volume and tonnage calculator converts any area and depth into yards and tons.
When to choose limestone screenings
Good uses:
- Paver and flagstone setting beds
- Firm walking paths
- Top-dressing a compacted stone base
Less suited to:
- Deep layers on their own
- Low spots that collect water
- Under heavy vehicle traffic without a base
Quick reference numbers
- Per inch over 100 sq ft: about 0.43 tons of limestone screenings (0.31 cubic yards).
- Per inch over 1,000 sq ft: about 4.3 tons.
- Another size for comparison: a 8x16 area at 2 inches takes about 1.1 tons.
- Weight used here: about 1.4 tons per cubic yard.
Common estimating mistakes
- Skipping drainage. Water sitting under any surface softens the base and leads to ruts and potholes.
- Measuring only the main rectangle. Aprons, turnouts and curved edges add real square footage.
- Ignoring the base. A thin surface layer over soft soil fails early no matter how much material is on top.
- Using inches as if they were feet. Depth has to be divided by 12 before you multiply; skipping that step inflates the order twelvefold.
Questions people ask
How many tons is 12 yards of limestone screenings?
About 16.8 tons, with a typical range of 15.6 to 18.0.
How many pounds is 12 cubic yards of limestone screenings?
About 33,600 pounds.
How much area does 12 yards of limestone screenings cover at 2 inches?
About 1,944 square feet.
Why does limestone screenings weight vary?
Stone size, the share of fines and moisture all change how much a yard weighs.
Is it better to buy by the ton or the yard?
Either works; just convert with the supplier’s own weight per yard so the two quotes compare fairly.
Related guides
- #10 Stone (Stone Dust): Size, Uses and How Many Tons
- Tons to Cubic Yards for Gravel: Conversion Chart
- How Much Does a Yard of Crushed Stone Weigh?
- 10 Cubic Yards of Limestone Screenings in Tons
- 11 Cubic Yards of Limestone Screenings in Tons
As an Amazon Associate, AsphaltTons.com earns from qualifying purchases. Product links below are sponsored.