AsphaltTons.com — asphalt tonnage calculator

How Much Crusher Run for a 20x40 Parking Pad?

How much crusher run for a 20x40 parking pad: at 4 inches deep you need about 9.88 cubic yards, which is roughly 15.3 tons at 1.55 tons per yard. The parking pad covers 800 square feet, so every inch of depth adds about 2.47 yards.

Volume and tonnage calculator →

The math for a 20x40 parking pad

  1. Area: 20 × 40 = 800 sq ft.
  2. Depth in feet: 4 ÷ 12 = 0.333 ft.
  3. Cubic feet: 800 × 0.333 = 266.7 cu ft.
  4. Cubic yards: ÷ 27 = 9.88 yd³.
  5. Tons: × 1.55 = 15.3 tons.

The volume and tonnage calculator does this for any size.

Crusher run needed by depth

DepthCubic yardsTons (approx.)Tons +10%
3 in7.4111.512.6
4 in9.8815.316.8
6 in14.8123.025.3
8 in19.7530.633.7

About crusher run

Crusher run (also sold as crush and run, dense-grade aggregate or QP in some regions) mixes stone with stone dust. It compacts into a firm, nearly solid layer, which makes it the usual base under pavers, asphalt and gravel drives. Ask your supplier for their own tons-per-yard figure, since stone source and moisture shift it.

Preparing the parking pad

Dig out organic soil, compact the subgrade and set an edge so the stone does not migrate onto the lawn. A pad that holds parked weight for long periods benefits from a dense base under the surface stone. For parked vehicles, the depths in the table above are a reasonable starting range.

Ordering tips

  • Round up. Compaction and uneven ground eat material. Adding about 10 percent is common.
  • Delivery size. 16.8 tons may take more than one typical dump truck load; small loads may carry a delivery fee. See how many tons of gravel in a dump truck.
  • Bulk vs bags. At this size bulk delivery is usually the practical choice.
  • Where it drops. Have the truck dump as close to the parking pad as firm ground allows.

Good and poor uses for crusher run

Good uses:

  • Base under asphalt, pavers or concrete
  • Gravel drives that need a firm, packed surface
  • Shed pads and equipment pads

Poor fit for:

  • Drainage layers, since the fines slow water
  • Decorative beds
  • Spots where you want water to soak straight through

Quick reference numbers

  • Per inch over 100 sq ft: about 0.48 tons of crusher run (0.31 cubic yards).
  • Per inch over 1,000 sq ft: about 4.8 tons.
  • Another size for comparison: a 14x28 area at 3 inches takes about 5.6 tons.
  • Weight used here: about 1.55 tons per cubic yard.

Mistakes that throw off the order

  • Skipping drainage. Water sitting under any surface softens the base and leads to ruts and potholes.
  • Ordering exactly the math. Uneven ground and spillage nearly always need a little more than the flat calculation.
  • Mixing up cubic yards and tons. Yards are volume, tons are weight; convert with the product’s weight per yard.
  • Measuring only the main rectangle. Aprons, turnouts and curved edges add real square footage.

Questions people ask

How many tons of crusher run for a 20x40 parking pad?

About 15.3 tons at 4 inches deep, or 16.8 tons with 10 percent extra.

How many cubic yards is a 20x40 parking pad at 4 inches?

About 9.88 cubic yards.

How much does a cubic yard of crusher run weigh?

Usually around 1.5 to 1.7 compacted tons, depending on stone size, fines and moisture.

How deep should crusher run be for a parking pad?

The table above shows 3 to 8 inches. Shallower depths suit top dressing; deeper depths suit new installs and heavier use.

How many square feet is 20x40?

800 square feet.

Related guides

Open the volume and tonnage calculator → Asphalt tonnage calculator →

As an Amazon Associate, AsphaltTons.com earns from qualifying purchases. Product links below are sponsored.