How Much Crusher Run for a 20x90 Driveway?

How much crusher run for a 20x90 driveway is a quick volume problem. 1,800 square feet at 4 inches comes to 22.22 cubic yards. Crusher run usually weighs about 1.5 to 1.7 compacted tons per cubic yard, so plan on roughly 34.4 tons.

Volume and tonnage calculator →

The math for a 20x90 driveway

  1. Area: 20 × 90 = 1,800 sq ft.
  2. Depth in feet: 4 ÷ 12 = 0.333 ft.
  3. Cubic feet: 1,800 × 0.333 = 600.0 cu ft.
  4. Cubic yards: ÷ 27 = 22.22 yd³.
  5. Tons: × 1.55 = 34.4 tons.

The volume and tonnage calculator does this for any size.

Crusher run needed by depth

DepthCubic yardsTons (approx.)Tons +10%
3 in16.6725.828.4
4 in22.2234.437.9
6 in33.3351.756.8
8 in44.4468.975.8

About crusher run

Crusher run (also sold as crush and run, dense-grade aggregate or QP in some regions) mixes stone with stone dust. It compacts into a firm, nearly solid layer, which makes it the usual base under pavers, asphalt and gravel drives. Ask your supplier for their own tons-per-yard figure, since stone source and moisture shift it.

Preparing the driveway

Strip sod and soft topsoil, grade for drainage and compact the subgrade before any stone goes down. Gravel drives last longer with a compacted base layer under the top stone and a slight crown so water runs off. This driveway sees car and truck traffic, so match the depth to that load rather than to the minimum.

Ordering tips

  • Round up. Compaction and uneven ground eat material. Adding about 10 percent is common.
  • Delivery size. 37.9 tons may take more than one typical dump truck load; small loads may carry a delivery fee. See how many tons of gravel in a dump truck.
  • Bulk vs bags. At this size bulk delivery is usually the practical choice.
  • Where it drops. Have the truck dump as close to the driveway as firm ground allows.

Where crusher run fits

Works well for:

  • Base under asphalt, pavers or concrete
  • Gravel drives that need a firm, packed surface
  • Shed pads and equipment pads

Poor fit for:

  • Drainage layers, since the fines slow water
  • Decorative beds
  • Spots where you want water to soak straight through

Quick reference numbers

  • Per inch over 100 sq ft: about 0.48 tons of crusher run (0.31 cubic yards).
  • Per inch over 1,000 sq ft: about 4.8 tons.
  • Another size for comparison: a 20x25 area at 2 inches takes about 4.8 tons.
  • Weight used here: about 1.55 tons per cubic yard.

Common estimating mistakes

  • Ignoring the base. A thin surface layer over soft soil fails early no matter how much material is on top.
  • Ordering exactly the math. Uneven ground and spillage nearly always need a little more than the flat calculation.
  • Using inches as if they were feet. Depth has to be divided by 12 before you multiply; skipping that step inflates the order twelvefold.
  • Forgetting that compaction shrinks loose material. A loose 4-inch spread of a dense-graded stone may finish closer to 3 inches after rolling.

Questions people ask

How many tons of crusher run for a 20x90 driveway?

About 34.4 tons at 4 inches deep, or 37.9 tons with 10 percent extra.

How many cubic yards is a 20x90 driveway at 4 inches?

About 22.22 cubic yards.

How much does a cubic yard of crusher run weigh?

Usually around 1.5 to 1.7 compacted tons, depending on stone size, fines and moisture.

How deep should crusher run be for a driveway?

The table above shows 3 to 8 inches. Shallower depths suit top dressing; deeper depths suit new installs and heavier use.

How many square feet is 20x90?

1,800 square feet.