Tons of Crusher Run per Mile of 18 ft Road
Tons of crusher run per mile of 18 foot road: about 2,728 tons at 6 inches deep. The strip is 18 ft × 5,280 ft = 95,040 square feet. Long runs magnify small depth changes, so pin the depth down before ordering.
Volume and tonnage calculator →Tons by depth
| Depth | Tons | Truckloads (~14 t) |
|---|---|---|
| 3 in | 1,364 | 98 |
| 4 in | 1,819 | 130 |
| 6 in | 2,728 | 195 |
| 8 in | 3,637 | 260 |
The math
- Area: 18 × 5,280 = 95,040 sq ft.
- Volume at 6 in: 95,040 × 0.500 = 47,520 cu ft (1,760 cubic yards).
- × 1.55 tons per yard = 2,728 tons.
What goes into the section
A 18-foot width allows two vehicles to pass carefully. Crusher run (also sold as crush and run, dense-grade aggregate or QP in some regions) mixes stone with stone dust. It compacts into a firm, nearly solid layer, which makes it the usual base under pavers, asphalt and gravel drives. Crown the surface so water sheds to ditches on both sides.
Practical notes
- Phasing. Large tonnages are delivered over days; schedule spreading and compaction to keep up with trucks.
- Waste. Allow 5 to 10 percent.
- Hauling. Distance from the quarry or plant often costs as much as the material on long jobs; see asphalt hauling cost per ton.
Check other sizes with the volume and tonnage calculator.
When to choose crusher run
Best suited to:
- Base under asphalt, pavers or concrete
- Gravel drives that need a firm, packed surface
- Shed pads and equipment pads
Poor fit for:
- Drainage layers, since the fines slow water
- Decorative beds
- Spots where you want water to soak straight through
Quick reference numbers
- Per inch over 100 sq ft: about 0.48 tons of crusher run (0.31 cubic yards).
- Per inch over 1,000 sq ft: about 4.8 tons.
- Another size for comparison: a 15x30 area at 2 inches takes about 4.3 tons.
- Weight used here: about 1.55 tons per cubic yard.
Common estimating mistakes
- Forgetting that compaction shrinks loose material. A loose 4-inch spread of a dense-graded stone may finish closer to 3 inches after rolling.
- Assuming every supplier uses the same weight. Two yards selling the same product name can quote different tons per yard.
- Using inches as if they were feet. Depth has to be divided by 12 before you multiply; skipping that step inflates the order twelvefold.
- Ordering exactly the math. Uneven ground and spillage nearly always need a little more than the flat calculation.
Questions people ask
How many tons of crusher run per mile of 18 ft road?
About 2,728 tons at 6 inches.
How many truckloads is that?
About 195 loads at roughly 14 tons each.
How many square feet is mile of 18 ft road?
95,040 square feet.
Should I add extra for waste?
Yes, 5 to 10 percent is common.
Does this include the shoulders?
No. Measure shoulders and pullouts separately and add them.
Related guides
- How Many Tons of Gravel in a Dump Truck? Loads and Coverage
- Asphalt Hauling Cost Per Ton: What Drives the Delivered Price
- Crushed Stone vs Gravel: Differences and Best Uses
- Tons of Crusher Run per Mile of 16 ft Road
- Tons of Crusher Run per 100 Feet of 16 ft Road
As an Amazon Associate, AsphaltTons.com earns from qualifying purchases. Product links below are sponsored.