How Much Crusher Run for 1,200 Square Feet?

How much crusher run for 1,200 square feet depends on depth. At 6 inches you need about 22.22 cubic yards, roughly 34.4 tons at 1.55 tons per yard. At 3 inches the order drops to 17.2 tons.

Volume and tonnage calculator →

Crusher run for 1,200 sq ft by depth

DepthCubic yardsTonsTons +10%
3 in11.1117.218.9
4 in14.8123.025.3
6 in22.2234.437.9
8 in29.6345.950.5

Working it out

  1. 1,200 sq ft × (6 ÷ 12) ft = 600.0 cubic feet.
  2. ÷ 27 = 22.22 cubic yards.
  3. × 1.55 tons per yard = 34.4 tons.

About crusher run

The fines in crusher run fill the gaps between stones, so it weighs more per yard than clean stone once compacted. Plan on rolling or plate-compacting it in lifts. Expect the weight to fall in the range of 1.5 to 1.7 compacted tons per yard.

Getting the order right

  • Measure odd shapes in pieces. Split curves and L-shapes into rectangles and add them.
  • Add a margin. About 10 percent covers compaction and low spots.
  • Bulk or bags. Bulk delivery is the practical choice here.
  • Prep first. Remove sod, compact the subgrade and set edging before the stone arrives.

Use the volume and tonnage calculator for any other size.

When to choose crusher run

Good uses:

  • Base under asphalt, pavers or concrete
  • Gravel drives that need a firm, packed surface
  • Shed pads and equipment pads

Think twice for:

  • Drainage layers, since the fines slow water
  • Decorative beds
  • Spots where you want water to soak straight through

Quick reference numbers

  • Per inch over 100 sq ft: about 0.48 tons of crusher run (0.31 cubic yards).
  • Per inch over 1,000 sq ft: about 4.8 tons.
  • Another size for comparison: a 15x30 area at 2 inches takes about 4.3 tons.
  • Weight used here: about 1.55 tons per cubic yard.

Common estimating mistakes

  • Assuming every supplier uses the same weight. Two yards selling the same product name can quote different tons per yard.
  • Mixing up cubic yards and tons. Yards are volume, tons are weight; convert with the product’s weight per yard.
  • Measuring only the main rectangle. Aprons, turnouts and curved edges add real square footage.
  • Ordering exactly the math. Uneven ground and spillage nearly always need a little more than the flat calculation.

Questions people ask

How many tons of crusher run for 1,200 square feet?

About 34.4 tons at 6 inches deep.

How many cubic yards of crusher run for 1,200 square feet?

About 22.22 yards at 6 inches.

How much crusher run for 1,200 square feet at 3 inches?

About 17.2 tons, or 11.11 cubic yards.

How much does a yard of crusher run weigh?

About 1.5 to 1.7 compacted tons.

Should I add extra?

Yes, about 10 percent is a common allowance.